Khutsong-04-Old Reservoir Boundary Wall

This project’s Site handover was on the 14 March 2017 and it was supposed to be a 20 month project, this means that the completion date of the project was to be on November 2018. The Project consisted of the following structures:

  • 30 Mega litre Concrete Reservoir
  • 235m long Access Road
  • Old Boundary Brick Wall
  • New Boundary Brick Wall
  • 300mm HDPE Pipeline
  • Caretaker House and Pump House. The only structure that is on the critical path is the Reservoir. Caretaker House and the Pump House are on hold until the completion of some sections of the Reservoir.