Scope of Work

  • Reconstruction of existing pavement structure:
    1. Milling of existing 30mm Asphalt to top of base
    2. Cut 200mm to stockpile for subbase re-use
    3. Construct 150mm road bed
    4. Transport 200mm from stockpile
    5. BSM1 stabilised sub-base
    6. 100mm thick BTB
    7. 40mm AE2 Asphalt
  • Installation of storm water pipes and associated drainage
  • Installation of Fig 3, Fig 8 kerbs
  • Reconstruction of sidewalks and pedestrian ramps